Business owners planning a tenant improvement in Phoenix, Arizona often hear that a commercial building permit takes about 30 days. According to Mike Marden, a registered architect and licensed general contractor who founded WDS, a Phoenix-based integrated design-build firm, that figure is a reasonable starting point but rarely reflects the full time between deciding to submit plans and holding an approved permit.
Marden says owners are usually caught off guard by the steps surrounding the city's review rather than the review itself, and most of those steps never appear in a published timeline. He works from 30 days as the default for the first review of a typical tenant improvement permit, but the answer depends on which city is reviewing the plans. The Phoenix area has roughly 20 municipalities, and WDS works regularly in six to eight of them. Each publishes review cycles a little differently. Some list calendar days, others count business days, and some city offices are only open Monday through Thursday. A review published as 27 business days at a city that does not work Fridays can stretch to five or six weeks on the calendar. Because of that, Marden says his team plans around the published worst case.
The bigger gap, according to Marden, is that a published review period usually covers only the technical review. Two other steps happen around it. The first is preparing the submittal. Most municipalities require plans to be submitted online through the city's public portal, and each has its own rules for organizing files. Some want each discipline uploaded separately, others want individual sheets broken out, and some let applicants save an application in progress while others require it to be completed in one sitting. Marden says this preparation can take as much as several days, depending on whether an account has been set up.
The second is an administrative review. Before plans go to technical reviewers, city technicians check whether the submittal is complete, sending email notification if a form is missing or an item should be added to the plan. Marden says that check can take anywhere from three to 15 days and is generally not counted in the published review time. Only after it clears does the three- or five-week technical review begin.
Once plans are in the city's hands, there is little an owner can do to speed up the review. Marden says the real time savings come earlier, during design, and depend largely on how quickly owners provide information and make decisions. Owners who follow the design team's process and complete action items on time move into city review sooner than those still deciding.
Marden also points to a gap unrelated to the city: the time between getting plans approved and deciding who will build the project. If bids come back higher than expected, an owner may want design changes, and revisions extend the review; significant changes can require the submittal to start over. For a commercial project, the city will not release the permit until the owner names a licensed general contractor with a proper commercial license. An owner who has not selected a contractor may go through a 30-day bid cycle while an approved permit waits and lease or mortgage payments continue on a space that cannot be built out yet. This is one reason Marden's firm keeps design and construction on the same team, with plans prepared through WDS Architecture and costs reviewed as the design develops, so the permit can be released as soon as it is approved.
For owners planning a buildout in the Phoenix area, Marden's advice is to build these steps into the schedule from the start: plan for the published worst case, allow time for submittal preparation and administrative review, and have a contractor in place before the permit is ready to be issued. WDS is comprised of WDS Architecture PLLC and WDS Commercial LLC, subsidiaries of Marden Companies LLC.